Key Points
North-South Corridor viaduct delayed to 2029, tunnel to 2031 due to harder-than-expected rock and groundwater at Novena and Woodlands.
Over 90 percent of foundation works completed by August 2026 with construction progressing to above-ground structures.
Roads and footpaths will reopen in phases from 2028 as major works complete, easing disruption before full opening.
The 21.5km corridor connects northern towns to city centre and will relieve congestion on Singapore's north-south transport axis.
Singapore’s North-South Corridor will open two years later than originally planned. The Land Transport Authority said on September 17 that the 8.8km viaduct will now open from 2029 instead of 2027, while the 12.3km tunnel section will open from 2031 instead of 2029. Unexpectedly difficult ground conditions, including harder rock and underground water at key sites, forced LTA to adopt more time-intensive construction methods.
What caused the two-year delay
LTA encountered harder-than-expected rock formations and groundwater seepage at multiple locations. At Gambas Avenue and Woodlands Avenue 8, foundation piles took longer to complete because rock levels were higher and harder than planned. At Novena, fractured rock and water inflows beneath the operational North-South MRT line required a more precise mining method to excavate in smaller sections instead of direct tunnelling. LTA said this section has clearance as close as one meter between the new tunnel and the existing MRT line.
Construction progress and phased reopenings
More than 90 percent of foundation works for both the viaduct and tunnel were completed by August 2026. Construction is now progressing to above-ground structures like columns, crossheads and viaduct segments. From 2028, roads, footpaths and areas affected by construction will reopen in stages. Noise barriers will start coming down from 2028, and pedestrian overhead bridges will be reinstated from 2029. For technically complex sections near Thomson Road and the Pan Island Expressway interchange, reinstatement is expected from 2030.
The 21.5km corridor’s role in Singapore’s transport network
The North-South Corridor is designed to improve connectivity between northern towns including Sembawang, Yishun, Ang Mo Kio, Toa Payoh, Novena and Rochor, and the city centre. The project comprises an elevated viaduct and an underground tunnel section. LTA said the corridor will relieve traffic along Singapore’s north-south transport axis and major arterial roads. Construction began in 2018 and has progressed through foundation work to the more complex structural installation phase.
What this means for commuters and businesses
The delay extends disruption along the corridor but progressive reinstatement of roads and footpaths from 2028 will ease conditions before the full opening. Businesses and residents in affected areas face at least three more years of construction activity. Once operational, the corridor is expected to significantly reduce travel times between the north and city, though the exact impact on property values and business activity remains uncertain until the viaduct opens in 2029.
Final Thoughts
The two-year delay reflects the engineering complexity of building major transport infrastructure in a densely developed city. Investors and businesses should factor the extended timeline into long-term planning for northern Singapore developments.
FAQs
Unexpectedly difficult ground conditions required more complex construction methods. Harder rock at Gambas Avenue and fractured rock with water seepage at Novena forced LTA to adopt slower, more precise mining techniques.
The viaduct will open in phases from 2029 and the tunnel from 2031. Previously, LTA had planned the viaduct for 2027 and tunnel for 2029.
The corridor links northern towns including Sembawang, Yishun, Ang Mo Kio, Toa Payoh, Novena and Rochor to the city centre via an 8.8km viaduct and 12.3km underground tunnel.
Roads and footpaths will progressively reopen from 2028. Noise barriers come down from 2028, and pedestrian bridges return from 2029. Technically complex sections near Thomson Road reopen from 2030.
Disclaimer:
The content shared by Meyka AI PTY LTD is solely for research and informational purposes. Meyka is not a financial advisory service, and the information provided should not be considered investment or trading advice.
About Author

Huzaifa Zahoor
Co FounderHuzaifa Zahoor is the engineer who built Meyka. He has spent years writing Python, training AI models, and building data pipelines specifically for financial markets. His technical articles have reached over 30,000 readers on Medium, so he knows how to make complex things easy to follow. If this article touches on how the tools work, he is the person who actually built them.
What brings you to Meyka?
Pick what interests you most and we will get you started.
I'm here to read news
Find more articles like this one
I'm here to research stocks
Ask Meyka Analyst about any stock
I'm here to track my Portfolio
Get daily updates and alerts (coming March 2026)